- Client
- Clearmark Construction
- Industry
- Construction and licensed asbestos removal
- Duration
- January 2025
- Standard
- AS/NZS ISO 45001:2018, AS/NZS ISO 9001:2016 and AS/NZS ISO 14001:2016
Key result: Integrated system built and rolled out, with inductions, management review and internal audit, in January 2025

The challenge
The contractor needed an integrated management system to support its demolition licence.
What we did
Developed an integrated health, safety, environmental and quality management system
Wrote an asbestos removal control plan, SWMS for asbestos removal, demolition and general construction, and high-risk work permits
Ran HSEQ inductions and an HSEQ meeting, then a management review
Carried out an internal audit against ISO 45001 and issued a compliance letter
The result
- Integrated system in place, with 2 HSEQ inductions completed on 17 January 2025
- Management review held 20 January 2025; internal audit completed 22 January 2025
- Internal audit raised 4 items, all closed out
Watch: What is an integrated management system?
Led by
Need help with integrated management systems?
Searching for a First-Class Safety Consultant?
Get in touch with our team to discuss your workplace safety needs.